The Schoharie Creek Aqueduct originally consisted of 14 stone arches for the towing path on the north side, thirteen piers on the south side, and two abutments at the ends. No longer needed after the completion of the Barge Canal, the wooden trunk of the Aqueduct was removed in c.1915/1916. In the summer of 1941, one arch fell into the river, causing the state to remove four additional arches in order to prevent an obstruction of the waters of Schoharie Creek. Additional arches collapsed during a 1977 flood, and again in 1998, threatening the stability of the rest. Six arches and portions of three piers remain standing today.
In December 2022, construction began on a project to stabilize the remaining arches of the Aqueduct. The stabilization project involved extensive repairs to the Aqueduct's foundation and structure. As part of the stabilization efforts, the towpath arches have been firmly secured using twelve piles, each approximately 65 feet deep. These piles were topped with a substantial 65-ton concrete block strategically positioned at the base of pier six, the easternmost of the interconnected piers. This anchoring system ensures the long-term stability of the arches. Furthermore, the restoration team went above and beyond expectations by meticulously repointing over 3,200 linear feet of the Aqueduct's masonry joints. In addition to the structural enhancements, the Aqueduct now benefits from large concrete anti-scour pads installed beneath arches four and six. To bolster anti-scour protection, stones from previous Aqueduct collapses have been strategically placed at key locations around the remaining structures. Moreover, surplus stones from past incidents have been creatively repurposed as park furniture in the Aqueduct Picnic Area. [From a press release of the New York State Office of Parks, Recreation and Historic Preservation, June 2nd, 2023.]
Selected pages from the official Construction Documents (Courtesy of the New York State Office of Parks, Recreation and Historic Preservation)
Stabilization activities at Arch 6 of the Schoharie Creek Aqueduct -- taken by Howard Ohlhous, Jan. 28, 2023. |
Stabilization work was finished on May 2nd, 2023 on schedule. In addition to the obvious work on the arches, 3,200 feet of repointing of the stonework was done.
Below are images of the completed project before the Spring re-watering of the area.
East end of the Schoharie Creek Aqueduct after stabilization --
Taken April 25, 2023 by Ted Olsen. |
The Otis Eddy Stone at the eastern end of the Aqueduct, after stabilization was complete, June 2023 -- Courtesy of the NYS Office of Parks, Recreation, and Historic Preservation. Note that the repointing of the joints between the stones is visible. A closeup of the engraving on the stone. |
http://www.eriecanal.org/SchoharieAqueductStabilization.html