HISTORY OF THE BARGE CANAL
OF NEW YORK STATE

BY NOBLE E. WHITFORD


CHAPTER XXXII

TABLES OF CONTRACTS

Construction of Barge Canal: Erie, Champlain and Oswego Canals, Work Completed and Work under Contract; Cayuga and Seneca Canal, Work Completed -- Construction of Barge Canal Terminals: Work Completed and Work under Contract.

In order not to burden the text of the present volume with too great detail, the contracts under which the Barge canal and terminal construction work was performed have been listed in tabular form and are here inserted under a special chapter heading. From these tables it may be learned when the work at the various localities was undertaken and also what the cost was. There are summaries which give the total costs. It should be said that all these figures represent the cost of construction and do not include engineering, the purchase of land, awards for damages and interference with vested rights, and other incidental expenditures. The tables show that virtually all canal construction is completed, while on terminal construction, especially the installation of machinery, considerable is still under contract. The logical arrangement in the tables has seemed to be that of contract number, but since no very definite or easily-explainable system was employed in the original assignment of numbers, search for any given piece of work will have to made until it is found.

It will be seen that the total construction cost of the Erie, Champlain and Oswego branches of the Barge canal, as shown in the following tables, is $96,685,570. In 1903 is was estimated that this cost would be approximately $84,000,000, but in 1915 it was evident that this amount would be exceeded, and the reasons therefor are given ... [in chapter 10] of this volume. Since that time there have been some other extraordinary increases in cost of labor and material, brought about by World war conditions, which tended very materially to increase the total cost of the construction work above either the 1903 or the 1915 estimates.


TABLES OF CONTRACTS:



CONSTRUCTION OF THE BARGE CANAL
WORK COMPLETED ON THE ERIE, CHAMPLAIN AND OSWEGO CANALS UP TO OCTOBER 18, 1922*,
EXCLUSIVE OF THAT DONE UNDER CHAPTER 585, LAWS OF 1918
[*The date has no significance aside from the fact that the tables were compiled then.]

Con-
tract
No.
Canal Description of work Contractor Date of
contract
Total con-
struction
cost, includ-
ing altera-
tions and
extra work
orders
1 Champlain Northumberland to Fort Miller, and Crockers Reef to Port Edward Empire Engineering Corporation 4/18/05 $479,875
2 Erie Locks 2 and 3 and prism through Waterford The Ferguson Contracting Co. 4/3/05 725,630
2-E Erie Completion of Contract 2 Holler & Shepard 12/8/09 286,135
2-G Erie Taintor gate, etc., Waterford side-cut A.A. Parker 10/17/16 11,590
3 Champlain Lock 6 and land line, Fort Miller to Crockers Reef Sundstrom & Stratton 4/4/05 688,129
4 Erie 4 3/4 miles east of Oneida lake Empire Engineering Corporation 4/18/05 732,657
4-B Erie Bridge on Burdick's road adjacent to Contract 4 E.J. Doyle & Co. 12/1/10 1,332
5 Erie Mosquito Point to Fox Ridge Empire Engineering Corporation 4/18/05 125,820
5-A Erie Completion of Contract 5 James Stewart & Co. 1/20/12 319,351
6 Erie N.Y.C.R.R. west of Rochester to South Greece F.A. Maselli 5/3/05 1,034,630
7 Erie and Champlain Superstructure of highway bridges, Contracts 2, 3, 4, 5 and 6 The Groton Bridge Co. 8/10/06 102,173
8 Erie Locks and dams at Scotia, Rotterdam and Cranesville Pittsburgh-Eastern Co. 5/22/06 920,776
8-A Erie Completion of lock and dam at Scotia The Foundation Co. 7/6/12 967,610
9 Erie Eagle Harbor to Medina Thomas Crimmins Contracting Co. 3/18/08 659,055
10 Oswego Locks and prism at Fulton McDermott Contracting Co. 6/7/06 670,379
10-A Oswego Completion of portion of Contract 10 The T.A. Gillespie Co. 12/14/11 168,583
10-B Oswego Completion of portion of Contract 10 Oswego Construction Co., Inc. 3/4/12 533,811
10-C Oswego Filling portion of old canal at Fulton Fulton Engineering Co., Inc. 11/18/14 39,904
11 Erie Locks 4, 5, and 6, guard-gate and prism, Waterford to Crescent Fort Orange Construction Co. 5/21/06 1,221,322
12 Erie Dredging, Oneida lake to Mosquito Point; Lock 23 James Stewart & Co. 9/23/07 3,105,781
13 Erie Superstructures of highway bridges, Contract 18 and part of Contract 12 Penn Bridge Co. 11/7/08 23,412
14 Erie Crescent to Rexford Flats; Mohawk river locks and dams Acme Engineering & Contracting Co. 9/10/07 2,676,042
14-A Erie Clearing lands between Crescent and Rexford Flats John Henkes 10/26/12 010
14-B Erie Completion of dams at Crescent and Vischer Ferry; removal of Crescent aqueduct Brown & Lowe Co. 10/29/14 88,169
14-R Erie Removal and reinterment of bodies in cemeteries Thomas F. Riley 11/28/11 629
15 Champlain Locks 11 and 12 and prism, Comstock to Whitehall Atlantic Gulf & Pacific Co. 8/9/06 1,388,171
16 Erie and Champlain Superstructures of highway bridges, Contracts 11, 25 and 27 The United Construction Co. 12/20/06 92,461
17 Erie Locks and dams at Amsterdam and Tribes Hill The Scofield Co. 12/29/06 53,794
17 Erie Locks and dams at Amsterdam and Tribes Hill (relet) Alexander Murdoch 3/3/08 754,269
18 Erie Lock 16, guard-gate and prism, Mindenville to Indian Castle Kelley Bros. Contracting Co. 1228/06 496,585
18-A Erie Completion of work, Mindenville and Little Falls (Contracts 18 and 20-A) N.Y. State Dredging Corporation 2/17/14 1,693,153
19 Erie Canal prism, Sulphur Springs to Tonawanda Great Lakes Construction Co. 11/26/06 825,083
20-A Erie Dredging, Mindenville to Little Falls Houston Barnard 8/20/09 321,491
20-B Erie Dredging, Canajoharie to Mindenville S. Pearson & Son, Inc. 8/2/09 1,018,359
20-C Erie Dredging, Yosts to Canajoharie American Pipe & Construction Co. 8/18/09 661,855
20-D Erie Dredging, Rexford Flats to Yosts American Pipe & Construction Co. 8/18/09 3,345,676
21 Erie Construction, Genesee river to N.Y.C.R.R. west of Rochester Lane Bros. Co. 4/7/10 949,000
22 Erie Superstructures of highway bridges, part of Contract 12 M. Fitzgerald 9/24/10 122,912
22-A Erie Substructure, etc., highway bridge at Weedsport Lupfer & Remick 8/8/12 27,870
23 Erie Locks 32 and 33 and prism, Kings Bend to Genesee river Millard & Lupton Co. 8/18/09 1,207,726
23-B Erie Completion of approaches, South Ave. bridge, Rochester Michael E. Sweeney 11/4/14 4,736
24 Champlain Guard-gate at Crockers Reef Kingsbury Construction Co. 11/1/11 43,841
25 Champlain Locks 9 and 10 and prism, Dunhams Basin to Comstock Atlantic Gulf & Pacific Co. 11/19/06 1,547,193
26 Champlain Dredging near Fort Edward The Lake Erie Dredging Co. 4/6/08 35,443
27 Champlain Locks 7 and 8 and prism, Fort Edward to Dunhams Basin The Kinser Construction Co. 11/23/06 393,535
27-A Champlain Completion of Contract 27 Holler & Shepard 12/1/10 548,764
27-B Champlain Diversion channel for Bond creek John J. Farrell, Jr. 5/23/16 6,043
29 Erie Lock 19 and prism, Sterling creek to Oneida-Herkimer Co. line Maryland Dredging & Contracting Co. 4/3/09 506,502
30 Erie Lock 18 and prism, Little Falls to Sterling creek Acme Engineering & Contracting Co. 7/16/09 2,913,187
30-A Erie Completion of work, Jacksonburg to Herkimer Mohawk Dredge and Dock Co., Inc. 11/24/16 124,461
31 Erie Lock 17, Rocky Rift dam and prism through Little Falls Casey & Murray 9/2/08 753,405
32 Champlain Needle beams, lock gates and valves, etc., Locks 6, 8 and 9 Penn Bridge Co. 4/19/09 44,375
33 Erie, Champlain and Oswego Needle beams, lock gates, guard and sluice gates, Contracts 2, 10, 11 and 15 Penn Bridge Co. 1/7/10 170,822
34 Erie Superstructure, Saratoga Ave. bridge, Waterford M. Fitzgerald 8/8/06 22,317
35 Oswego Locks 7 and 8 and prism through Oswego Gilmour-Horton-Allen Co. 9/16/07 676,101
36 Erie Operating winches for Mohawk river movable dams J.D. Miller 5/25/10 47,210
37 Oswego Locks 5 and 6 and prism, Fulton to Oswego Henry P. Burgard 12/9/10 2,609,680
37-R Oswego Removal of bodies from Minetto cemetery Sallidin & Henrick 11/29/12 3,682
38 Erie Highway bridge at Wappings, west of Fairport Henry Tosh & Son 1/11/09 16,635
39 Oswego Dredging, Three Rivers to Fulton James Stewart & Co., Inc. 4/15/10 969,803
40 Erie Lockport to Sulphur Springs guard-lock The United Engineering & Contracting Co. 11/27/08 2,113,231
41 Erie Embankment of Irondequoit creek Butler Bros. Construction Co. 12/5/08 241,741
42 Erie Lock 20 and prism, Oneida-Herkimer Co. line to Oriskany road Shanley-Morrissey, Inc. 7/9/09 478,670
42-A Erie Completion of Contract 42 Grant Smith & Co. & Locher 2/24/13 1,197,578
43 Erie Oriskany road to Mud creek The M.A. Talbott Co. 10/15/09 1,306,549
44 Erie Mud creek to east end of Contract 4 Scott Bros. 1/8/10 1,629,999
45 Erie Lock 24 and prism at Baldwinsville; dam at Caughdenoy Scott Bros. 5/6/08 419,519
46 Erie Lock 25 and prism, Fox Ridge to Seneca-Wayne Co. line The Kinser Construction Co. 11/23/08 842,689
46-A Erie Completion of Contract 46 from Fox Ridge to Montezuma aqueduct James Stewart & Co., Inc. 9/2/14 181,338
46-B Erie Completion of lock 25 Scott Bros. 2/25/16 270,974
47 Erie Lock 26 and prism, Seneca-Wayne Co. line to Lyons The Crowell-Sherman-Stalter Co. 11/30/08 833,442
47-A Erie Completion of Contract 47 Central Dredging Co. 3/22/16 193,720
48 Erie Locks 27 and 28-A and prism, Lyons to Newark The Sherman-Stalter Co. 12/29/10 1,482,999
49 Erie Lock 30 and prism, Yellow Mills bridge to Wayne-Monroe Co. line American Pipe & Construction Co. 2/21/10 797,544
50 Erie Dam and reservoir ant Hinckley on West Canada creek The Buffalo Dredging Co. 9/23/10 995,673
51 Erie Nine-Mile creek diverting dam and feeder The Alto Construction Co. 12/23/10 375,081
53 Oswego Lock 1 and prism, Phoenix Scott Bros. 8/16/09 165,689
54 Champlain Lock 7 at Fort Edward The Hunkin-Conkey Construction Co. 12/13/09 223,893
55 Erie Dam and reservoir at Delta on Mohawk river Arthur McMullen 10/19/08 884,811
55-R Erie Removal and reinterment of bodies in cemeteries Joseph Kalk & Alfred S. Brown 11/3/11 7,627
56 Champlain Improving the Glens Falls feeder Flood & Van Wirt Co. 9/26/12 333,542
57 Erie Dredging through Onondaga outlet N.Y. State Dredging Corporation 8/6/12 93,315
59-A Erie Sewers, Genesee Valley park to Court St., Rochester P.H. Murray 7/3/16 110,031
60 Erie South Greece to Adams Basin Empire Engineering Corporation 8/6/08 1,346,261
61 Erie Adams Basin to Monroe-Orleans Co. line Cleveland & Sons Co. 10/13/08 1,048,666
62 Erie Monroe-Orleans Co. line to Eagle Harbor I.M. Ludington's Sons, Inc. 8/11/10 2,854,348
63 Erie Wayne-Monroe Co. line to Kings Bend H.S. Kerbaugh, Inc. 6/3/10 2,993,209
64 Erie Medina to Gasport Empire Engineering Corporation 8/6/08 1,199,980
65 Erie Prism and structures at Medina Maryland Dredging & Contracting Co. 3/26/13 1,110,918
66 Erie Gasport to Lockport Empire Engineering Corporation 9/22/08 783,160
67 Erie Locks 33 and 34 and prism [original text says "prison"] at Lockport Larkin & Sangster 9/3/10 1,048,772
68 Champlain Locks 3, 4 and 5 and adjoining structures Shanley-Morrissey, Inc. 11/23/08 947,813
69 Champlain Lock 2 and adjoining structures I.A. Hodge & Co., Inc. 12/11/09 231,504
70 Champlain Dredging, Waterford to Lock 1 Shanley-Morrissey, Inc. 1/11/10 236,240
70-A Champlain Completion of Contract 70 Central Dredging Co. 10/22/12 798,842
71 Champlain Lock 1 and dam and dredging, Lock 1 to Lock 2 Shanley-Morrissey, Inc. 1/11/10 826,305
71-A Champlain Completion of Contract 71 P. McGovern & Co. 1/16/13 1,487,701
72 Champlain Dredging, Lock 2 to Lock 4 Shanley-Morrissey, Inc. 12/14/09 618,900
72-A Champlain Completion of contract 72 James Stewart & Co., Inc. 3/27/13 1,515,095
72-B Champlain Widening prism at mouth of Hoosic river James Stewart & Co., Inc. 7/7/16 92,517
73 Champlain Dredging, Lock 4 to Northumberland E.M. Graves 5/26/10 517,223
74 Erie Dredging Mohawk and Hudson rivers below lock 2, Waterford Dunbar & Sullivan Dredging Co. 2/13/14 215,741
75 Erie Guard-gates within limits of Contracts 60, 61 and 64 United Construction Co. 3/1/10 43,842
76 Erie Lock 28-B and prism, Newark to Port Gibson The T.A. Gillespie Co. 12/23/10 1,401,110
77 Erie Lock 29 and prism, Port Gibson to Yellow Mills The T.A. Gillespie Co. 12/23/10 1,691,466
78 Oswego Dike at Fulton Cunningham-Woodard Co. 4/18/10 50,119
79 Oswego Superstructure for highway bridge, Bridge St., Oswego Lupfer & Remick 9/23/10 34,661
80 Oswego Dam of Phoenix Walter Bradley 1/16/11 112,034
81 Erie Junction lock at Rome Chesley, Earl & Heimbach, Inc. 10/17/16 50,594
82 Erie Superstructures of highway bridges on Contract 21 Groton Bridge Co. 12/7/10 28,708
83 Erie Construction, Contract 19 to Niagara river, Tonawanda Mohawk Dredge & Dock Co. 10/22/17 164,191
85 Oswego Superstructure, lift-bridge, Bridge street, Phoenix Lupfer & Remick 8/5/11 12,339
86 Erie Bridge at Canajoharie Lathrop, Shea & Henwood Co. 9/23/11 39,164
87 Erie Lansing's bridge, Sta. 4078, Contract 20-A The P.B. McCaghey Co. 2/17/13 11,400
88 Champlain Reconstructing portion of bridge at Schuylerville Lathrop, Shea & Henwood Co. 11/4/11 30,844
89 Erie Bridges between Lyons and Palmyra, Contracts 48, 76 and 77 Owego Bridge Co. 5/28/12 56,205
90 Erie, Champlain and Oswego Power equipment, etc., Locks 24, Erie; 1,2,7,8, Oswego, and 9,11, 12, Champlain D'Olier Engineering Co. 4/12/10 178,733
90-A Oswego Power-plants, etc., at [original text has "a"] Locks 1,2,7 and 8, Oswego canal Lupfer & Remick 8/8/12 63,137
91 Erie Power-plant, east end of Crescent dam The Holington Co. 1/5/11 43,750
91-A Erie New governor equipment, Crescent power-house Lord Construction Co. 11/24/16 6,226
92 Erie and Champlain Power equipment Locks 2 to 19, incl., guard-gate above 6, Erie; 1 to 8, Champlain MacArthur Bros. Co. & Lord Electric Co. 2/17/13 1,209,394
93 Erie and Oswego Power equipment, Locks 20, 21, 22, 23 and 25, N. London junction lock, Erie; 3, 5 and 6, Oswego MacArthur Bros. Co. & Lord Electric Co. 8/12/13 364,305
94 Erie Power equipment, Locks 26, 27, 28-A, 28-B, 29, 30, 32, 33, 34, 35 and guard-locks, Erie MacArthur Bros. Co. & Lord Electric Co. 2/17/13 439,789
100 Erie and Oswego Bridges at Long Branch, Belgium and Hinmansville, Contracts 12, 39 and 57 W.J. Burns Co. 9/12/13 162,757
101 Erie Highway bridge at Three Rivers Barrally & Ingersoll 8/8/12 40,655
102 Erie Bridge superstructure at Howland's Island Lupfer & Remick 2/20/13 24,560
103 Oswego Concrete and bascule bridge at Lock St., Phoenix Barrally & Ingersoll 12/10/12 185,033
104 Oswego Reinforced concrete arch bridge at Broadway, Fulton R.B. Murdock 3/5/12 36,856
105 Erie Lift-bridges at Spencerport, Adams Basin, Brockport, Hulberton and Gasport Skene & Richmond 4/19/12 245,688
106 Erie Lift-bridges Brockport, Medina, Middleport and Lockport; and guard-gate at Gasport The W.S. Cooper Co. 5/13/14 274,268
107 Erie Lift-bridge and fixed bridge at Little Falls Jackson L. Richmond 2/19/13 115,093
108 Erie Highway bridges near Macedon and superstructures at Peeks' and Allerton's I.M. Ludington's Sons, Inc. 10/17/13 84,199
109 Erie Highway bridge at site of Crescent aqueduct Larkin & Sangster 7/31/14 151,371
110 Erie Highway bridges at James and Lawrence Sts., Rome Chesley, Earl & Heimbach, Inc. 12/3/15 124,239
112 Erie Steel sheet-piling and slope protection with Contracts 60 and 66 John Young 4/24/13 120,519
113 Erie Timber for trough at Bushnell's Basin and Holley Wm. J. Dowdle 4/15/13 21,971
114 Erie Guard-gate above Lock 6, Waterford Chas. A. Hager 10/7/13 36,908
115 Erie Superstructure of Movable dam 4, Scotia Penn Bridge Co. 10/28/14 97,042
116 Erie Bridges at toll road and County line, Contract 46 Walsh Construction Co. 1/16/14 77,284
117 Oswego Bascule bridge over Lock 2, Fulton Walter S. Rae 4/15/18 32,299
118 Erie Bridge over Mohawk at Amsterdam Lathrop, Shea & Henwood Co. 7/29/14 154,611
119 Erie Driving steel sheet-piling cut-off and extending apron, Dam 5, Rotterdam Holler & Shepard 8/4/14 50,567
120 Erie Changes in Movable dams 5 to 11, inclusive, Mohawk river Whitehead & Kales Iron Works 7/29/14 382,026
121 Erie Superstructure of bridge at Sta. 2901 + 83, Contract 12 General Erecting Co. 7/8/14 9,110
122 Erie Highway bridge over Mohawk below Little Falls, Sta. 4246 + 42 Thomas Leonard 2/23/16 6,090
123 Erie Dam and sluice gate across West Canada creek at Trenton Falls Frank L. Cohen 5/11/14 17,530
125 Erie Viaduct over railroad at Vischer Ferry Keith O. Guthrie 8/31/14 39,178
126 Champlain Raising existing bridge at Mechanicville Horseheads Construction Co. 9/4/14 6,101
128 Champlain Highway bridge at Northumberland Holler & Shepard 5/27/16 75,189
129 Erie Freeman's bridge at Schenectady The Foundation Co. 6/6/16 82,202
130 Erie Improvement of Albany basin Great Lakes Dredge & Dock Co. 4/3/16 5,506
131 Champlain Bridge at Schuylerville Spaulding Construction Co. 3/28/16 850
131-A Champlain Completing bridge at Schuylerville M. Fitzgerald 3/5/17 37,916
132 Erie Lighthouses, buoys, etc., for Oneida and Onondaga lakes Lupfer & Remick 11/3/16 69,669
133 Erie Junction lock at Mohawk Morrison & Quinn, Inc. 10/16/16 42,435
135 Erie Excavating point below Dam 10, Canajoharie Great Lakes Dredge & Dock Co. 9/18/16 48,637
137 Erie Steel sheet-piling at Dam 10, Canajoharie J.A. LaPorte 10/13/16 17,866
139 Oswego Excavating channel below Lock 8, Oswego Empire Engineering Co., Inc. 11/3/16 17,837
140 Champlain Bank protection, Hudson river north of Waterford, Contract 71-A Holler & Shepard 11/1/16 4,856
144 Erie Red creek bridges, Genesee Valley park, Rochester W.F. Martens & Co., Inc. 6/14/17 6,580
144-A Erie Completing Contract 144 Brown & Lowe Co. & Law Bros. 8/27/19 67,733
145 Erie Raising existing Scotia Bridge, Schenectady. Horseheads Construction Co. 1/4/17 3,765
146 Erie New movable dam to replace Dam 14, Herkimer Peckham Construction Co., Inc. 4/18/18 89,934
147 Erie Bascule bridge, Main and Webster Sts., Tonawanda Lathrop, Shea & Henwood Co. 9/10/17 254,019
148 Erie Highway bridge across Lock 27, at Leach St., Lyons Lathrop, Shea & Henwood Co. 9/5/17 67,878
150 Erie Concrete apron below head gates at Vischer Ferry dam Brown & Lowe Co. 12/1/16 22,273
152 Erie Repairing Lock 35, Lockport Lupfer & Remick 11/15/19 119,597
153 Erie and Oswego Aids to navigation on Mohawk, Oneida, Seneca and Oswego rivers R.B. Wing & Son 2/28/17 4,389
154 Erie Additional Taintor gate at Lock 27, Lyons Lupfer & Remick 4/7/17 8,409
155 Erie Hoist for bulkhead gates, Vischer Ferry dam Lupfer & Remick 1/31/17 12,258
156 Erie Highway bridge across Wood creek near Sylvan Beach Chesley, Earl & Heimbach, Inc. 8/28/17 9,643
157 Erie Dam across old canal at Rome Thos. Bowen 4/20/17 5,954
158 Erie and Oswego Buoys and lamp posts for Mohawk, Oneida, Seneca and Oswego rivers James McKinney & Son 3/22/17 3,127
161 Erie Furnishing and delivering electric motors, etc. at Rochester Lord Construction Co. 8/3/17 16,687
162 Erie Drain across canal at Main St., Brockport Charles A. Ingersoll 3/27/17 6,456
164 Erie Completing work between Lyons and Newark, and dam at Macedon Lathrop, Shea & Henwood Co. 10/30/17 223,540
165 Erie Removing Montezuma aqueduct and completing excavation Mohawk Dredge & Dock Co., Inc. 11/23/17 146,114
167 Oswego Bascule bridge at Culvert St., Phoenix Walter S. Rae 10/13/17 28,425
168 Champlain Concrete guide piers near Locks 3, 5 and 6, Champlain canal Bronk & Kimmey 7/29/18 89,352
169 Champlain Temporary timber guide piers below Locks 3 and 6 Holler & Shepard 6/28/17 2,883
170 Erie Junction lock and excavation at South Greece Cleveland & Sons Co. 11/10/17 60,096
172 Erie Barrel buoys and lamp posts on Seneca, Clyde, Genesee and Tonawanda rivers Lupfer & Remick 3/15/18 13,819
173 Erie Lanterns for buoys, etc., on Seneca, Clyde and Genesee rivers R.B. Wing & Son 2/9/18 8,960
178 Erie Improvement of by-passes at Locks 32 and 33 W.F. Martens 3/12/18 47,272
179 Erie Completing excavation and incidental work near Pittsford I.M. Ludington's Sons, Inc. 11/9/17 91,409
180 Erie Removing Rexford Flats aqueduct Dunbar & Sullivan Dredging Co. 3/15/18 16,154
181 Erie Waterproofing canal bottom at Little Falls Law Brothers 12/28/17 48,223
182 Oswego Completing excavation in front of dockwall below Lock 8, Oswego E. Brown Baker 8/30/18 27,228
183 Erie Aligning bridge at W. Henrietta road, Rochester Donnell-Zane Co. 9/11/18 5,505
184 Erie Excavation under N.Y.C.R.R. bridge at Brewerton Mohawk Dredge & Dock CO. 4/12/18 9,563
185 Erie Channel improvement below dams at Scotia and Rotterdam Am. P. & Const. Co. (R. Wetherill, Rec'r) 6/24/18 151,541
187 Erie Bank protection between New London and Lock 22 Scott Bros. 8/20/18 15,585
188 Erie Completing excavation under Brewerton R.R. bridge E. Brown Baker 8/7/18 35,996
189 Erie Completing excavation and placing bank protection, Fairport to Kings Bend Lathrop, Shea & Henwood Co. 12/6/19 18,562
190 Erie Completing canal from Kings Bend to L.V.R.R. crossing, Rochester Empire Engineering Co., Inc. 3/20/19 244,307
191 Erie Completing work on Contract 59 in river south of temporary dam Empire Engineering Co., Inc. 1/14/19 155,023
192 Erie Completing work on Contract 59 in Genesee Valley park and east guard-lock to Genesee river Brown & Lowe Co. 1/22/19 593,286
194 Champlain Completing work on Contract 1-A, Crockers Reef to Fort Edward Dunbar [original text says "Dunber"] & Sullivan Dredging Co. 5/24/20 36,791
197 Erie Repairs to Dam 4 at Rotterdam Stewart Bros. 1/27/19 14,620
198 Erie Highway bridge below Lock 28-A, Lyons Lupfer & Remick 8/25/19 39,341
200 Erie Steel sheet-piling, etc., between Rochester and Lockport Lupfer & Remick 2/26/19 128,847
201 Erie Completing concrete lining at Cartersville and stream entrance near Knapp's bridge I.M. Ludington's Sons, Inc. 3/13/19 50,782
204 Erie Dam across old canal, Lexington Ave., Rochester I.M. Ludington's Sons, Inc. 3/19/20 3,168
205 Oswego Concrete spillway below Lock 3, Fulton Scott Bros. 3/20/21 40,465
206 Erie Raising bridge over Lock 33, Rochester Groot Engineering Co., Inc. 8/31/21 3,667
207 Erie Removing material from prism, Orr's bridge, east of Holley Byron, Forman & Riggs, Inc. 1/4/22 5,022
            Total ...................................................................... ................................... ............ $86,921,972


WORK COMPLETED ON THE ERIE, CHAMPLAIN AND OSWEGO CANALS UNDER CHAPTER 585, LAWS OF 1918
[This was the act which recompensed contractors for losses sustained by reason of doing work under war conditions on contracts entered into before war was declared.]

Con-

tract
No.
Canal Description of work Contractor Date of
contract
Total con-
struction
cost, includ-
ing altera-
tions and
extra work
orders
1-A Champlain Completing portion of Contract 1, Crockers Reef to Fort Edward Holler & Shepard 8/3/14 $212,255
19-A Erie Redredging Contract 19 Empire Engineering Co., Inc. 11/3/16 240,923
21-A Erie Completion of Contract 21 Walsh Construction Co. 2/16/16 631,401
23-A Erie Completion of Contract 23 Empire Engineering Co., Inc. 5/20/16 984,058
29-A Erie Completion of Contract 29 Eastover Construction Co., Inc. 3/27/16 376,443
44-A Erie Completion of work at New London Scott Bros. 10/10/16 56,242
59 Erie Rochester harbor and connecting channel MacArthur Bros. Co. 11/3/16 1,900,868
63-A Erie Completion of Contract 63 State Highway Const. Co. 2/23/16 456,595
73-A Champlain Completion of Contract 73 Great Lakes Dredge & Dock. Co. 1/15/16 580,096
84 Erie Viaduct over the river at Clyde Lupfer & Remick 3/9/17 92,421
98 Erie Lift-bridge at Adams St. and removing bridge at Chapel St., Lockport Tifft Construction Co., Inc. 11/24/16 84,723
99 Oswego Bascule bridge at Minetto Larkin & Sangster 9/12/16 153,086
122-A Erie Completing Contract 122 Chesley, Earl & Heimbach, Inc. 3/8/17 81,717
138 Erie Movable dam, etc., at Rochester Combined Construction Co. 4/19/17 716,030
141 Erie New power-station at Lock 29, Palmyra W.F. Maas & Son 3/8/17 27,193
159 Erie Embankment between Newark and Palmyra and extending Ganargua creek spillway I.M. Ludington's Sons, Inc. 3/27/12 40,046
            Total ...................................................................... ................................... ............ $6,634,097


WORK UNDER CONTRACT BUT UNCOMPLETED OCTOBER 18, 1922

Con-
tract
No.
Canal Description of work Contractor Date of
contract
Engineer's
preliminary
estimate
Contractor's bid
202 Erie Completing excavation and placing protection, Genesee river, Rochester James Stewart & Co., Inc. 5/4/22 .......... $339,902
208 Erie Taintor gate at Baldwinsville dam Troy Public Works, Inc. 6/12/22 .......... 27,387
209 Erie Raising Maguire's bridge approach within limits of Contract 62 .................... .......... $3,003 ..........
210 Erie Spillway at south end, movable dam, Herkimer Mohawk Dredge & Dock Co. 10/16/22 .......... 4,504
            Total ...................................................................... ................................... ............ $3,003 $371,793


TOTAL CONSTRUCTION COST OF THE ERIE, CHAMPLAIN AND OSWEGO BRANCHES OF THE BARGE CANAL

ITEMS Totals
Work completed exclusive of that done under chapter 585, Laws of 1918 ............... $86,921,972
Work completed under chapter 5858, Laws of 1918 ............... 6,634,097
Work under contract but uncompleted, October 18, 1922 ............... 371,793
3,003
Special work: Completing Contracts 47-A and 63-A, relocating highways and miscellaneous extra work ............... 2,724,305
Schenectady-Scotia bridge ............... 500,000
  ------------
  $97,155,170
Deduct bonds of the J.R. Shanley Estate Co., held by the Comptroller ............... 469,000
  ------------
        Total .............................. $96,685,570


WORK COMPLETED ON THE CAYUGA AND SENECA CANAL

Con-
tract
No.
Canal Description of work Contractor Date of
contract
Total con-
struction
cost, includ-
ing altera-
tions and
extra work
orders
A Cayuga and Seneca Lock and dam at Cayuga Scott Bros. 12/30/10 $352,845
A-1 Cayuga and Seneca Dam repairs and fish ladder at Dam 1, Cayuga The Sherman-Stalter Co. 7/24/16 24,750
B Cayuga and Seneca Montezuma to Cayuga lake, Cayuga lake to Seneca Falls, Waterloo to Seneca Falls The Sherman-Stalter Co. 12/29/10 1,313,169
C Cayuga and Seneca Locks, dams, etc., at Seneca Falls Larkin & Sangster 1/11/13 1,171,914
D Cayuga and Seneca Dredging Seneca river, Demont's bridge through Waterloo The Sherman-Stalter Co. 2/24/14 948,530
E Cayuga and Seneca Lock, dam, etc., at Waterloo Cleveland & Sons Co. 1/7/13 317,646
F Cayuga and Seneca Highway bridges at Lake road, Free bridge and Demont's Stanley Construction Co. 7/20/14 127,400
G Cayuga and Seneca Lock gates, valves, buffer-beams, needle-beam, Taintor and guard-gates, Locks 2, 3 and 4, dam 2 Lupfer & Remick 11/24/14 102,296
H Cayuga and Seneca Excavating Cayuga inlet at Ithaca N.Y. State Dredging Corporation 12/22/11 218,479
I Cayuga and Seneca Watkins to Montour Falls The Central Dredging Co. 9/23/12 187,350
J Cayuga and Seneca Bridge at Fourth St., and dockwall, Watkins Chesley, Earl & Heimbach, Inc. 11/27/14 45,122
K Cayuga and Seneca Highway bridges at Ovid and Bridge Sts., Seneca Falls, and Washington St., Waterloo The Phoenix Bridge Co. 10/30/14 60,480
L Cayuga and Seneca Highway bridges at Gorham St., Waterloo, and Kingdom road Scott Bros. 9/23/15 55,554
M Cayuga and Seneca Power-plants, equipment, etc., Locks 1,2,3 and 4 Lupfer & Remick 11/5/14 190,496
P Cayuga and Seneca Cut-off wall below walls of Lock 3, Seneca Falls The Foundation Co. 6/8/17 107,883
Q Cayuga and Seneca Pile dolphins on Cayuga and Seneca lakes W. F. Martens 3/3/19 5,092
R Cayuga and Seneca Completing unfinished work on Cayuga and Seneca canals The Sherman-Stalter Co. 4/30/18 173,434
T Cayuga and Seneca Extending core wall, Dam 2, Seneca Falls Kennedy & Scullen Const. Co., Inc. 1/20/19 18,721
U Cayuga and Seneca Repairing sewer in Benton creek, Seneca Falls Smith-Soper 1/3/19 5,148
W Cayuga and Seneca Placing fill along river bank above dam, Seneca Falls J. B. Anglim 3/5/21 4,461
        ------------ ------------
            Total ........................................ .............................. ............... $5,430,770


CONSTRUCTION OF BARGE CANAL TERMINALS
WORK COMPLETED UP TO OCTOBER 18, 1922, EXCLUSIVE OF THAT DONE UNDER CHAPTER 585, LAWS OF 1918
Chapter 746, Laws of 1911, and amendatory laws

Con-
tract
No.
Description of work Contractor Date of
contract
Total con-
struction
cost, includ-
ing altera-
tions and
extra work
orders
1 Dockwall at Ithaca New York State Dredging Corporation Aug. 21, 1912 $40,535 76
2 Dockwall at Albany Raymond Concrete Pile Company Aug. 30, 1912 140,474 79
2-P Paving at Albany Patrick W. Mulderry Nov. 12, 1915 30,545 20
3 Dockwall and grading, Little Falls Ætna Engineering and Contracting Co. Aug. 13, 1912 60,083 60
5 Dockwall and grading, Mechanicville E. Brown Baker Sep. 4, 1912 52,210 94
6 Dockwall and grading, Whitehall Albert M. Banker Nov. 22, 1912 46,995 70
7 Dockwall and grading, Fort Edward Aldrich & Hall, Inc. Oct. 3, 1912 45,741 27
7-A Approach channel and harbor, Fort Edward New York State Dredging Corporation Oct. 14, 1912 140,255 39
8 Dockwall and grading, Schenectady American Pipe and Construction Co. Oct. 14, 1912 157,745 68
8-P Paving at Schenectady terminal James P. Kelly April 15, 1918 8,452 69
9 Dockwall and grading, Herkimer Ætna Engineering and Contracting Co. Oct. 2, 1912 65,192 51
10 Dockwall and grading, Fonda American Pipe and Construction Co. Nov. 25, 1912 57,780 42
10-P Paving, Fonda terminal Patrick W. Mulderry April 12, 1918 8,054 40
11 Dockwall and grading, Ilion Ætna Engineering and Contracting Co. Nov. 25, 1912 54,728 79
12 Dockwall and grading, Amsterdam American Pipe and Construction Co. Nov. 25, 1912 59,808 02
12-F Fence along roadway approach, Amsterdam terminal Anchor Post Iron Works April 16, 1918 1,355 25
13 Guard-lock and highway bridge, Schuylerville Kendar Engineering & Construction Co. Dec. 29, 1914 * 78,283 37
14 Dockwall and grading, lower terminal, Troy Walsh Construction Co. Jan. 16, 1914 125,337 11
15 Lock channel, basin, dockwall and grading at Utica Eastover Construction Company Jan. 8, 1913 582,834 73
15-D Drainage of terminal site at Utica Mohawk Dredge & Dock Co., Inc. Aug. 13, 1917 9,276 09
15-M Lock machinery, Utica terminal Lupfer & Remick Oct. 31, 1917 37,069 72
16 Dockwall and grading, Rome M. A. Talbott Company Nov. 19, 1912 86,715 32
16-P Macadam pavement, Rome E. Brown Baker June 4, 1917 4,169 50
17 Raising dockwall and laying stone block pavement, Lockport John Johnson Construction Co. Dec. 4, 1912 48,906 89
18 Bulkhead and harbor at Gowanus bay Geo. W. Rogers & Co., Inc. July 15, 1914 323,204 40
19-P Paving at Greenpoint and West 53d street The Hastings Pavement Company April 14, 1920 23,329 09
21-P Paving, Erie basin, Buffalo Henry P. Burgard Company May 6, 1918 13,066 00
22 Dockwall at Fort Plain Leary & Morrison Co. Mar. 31, 1913 22,839 44
23 Pier at Plattsburgh D.L. Taylor & Co. Feb. 24, 1913 129,512 46
25 Pier at Port Henry New York State Dredging Corporation Aug. 27, 1913 89,638 84
26-A Completion of terminal at Rouses Point Holler-LaDu Corporation Nov. 11, 1920 28,739 40
27 Dockwall at Frankfort Ætna Engineering and Contracting Co. Aug. 27, 1913 41,249 16
27-P Paving, Frankfort terminal Patrick W. Mulderry April 12, 1918 3,938 45
28 Dockwall and breakwater at Cleveland Barrally & Ingersoll Feb. 15, 1915 34,553 77
28-A Protection of breakwaters at Cleveland Eugene Dawley Mar. 1, 1920 19,233 55
29 Proposed dockwall and breakwater at Constantia Barrally & Ingersoll Nov. 27, 1914 3,400 00
30 Dockwall, hydraulic canal wall and roadway approach, Oswego, river terminal Henry P. Burgard Mar. 24, 1916 101,789 20
33 Lake pier at Oswego Empire Engineering Co., Inc. July 10, 1914 338,252 26
33-P Paving at Oswego, lake terminal Guy P. Dickison May 7, 1918 11,329 00
34 Dockwall at Thomson Champlain Engineering and Construction Corporation Aug. 20, 1914 16,128 06
35 Dockwall at Crescent Joseph P. Casey Nov. 7, 1914 9,146 37
36-A Dockwall extension and freight-house at Cohoes Holler-LaDu Corporation Nov. 28, 1919 40,469 40
37 Dockwall, harbor and paving at Canajoharie Holler and Shepard Aug. 26, 1915 31,504 34
38 Pier at West 53d street, New York city I. J. Stander & Co., Inc. Oct. 27, 1917 262,654 44
39 Grading terminal site at Albion Fred H. Rhodey Mar. 19, 1917 2,718 40
40 Dockwall, harbor and approach, St. Johnsville Scott Bros. Sept. 20, 1915 25,542 91
41 Removing buildings and grading the terminal site at Troy, upper terminal Eastern Storage Transfer & Wrecking Corp. Nov. 29, 1918 480 80
42 Paving at Long Island City terminal Leonard Paving CO. Nov. 13, 1918 47,313 05
43 Dockwall, dredging, frame freight-house, Flushing McHard-Barton Company July 25, 1919 163,789 71
44 Dockwall, Mott Haven Geo. W. Rogers Co., Inc. June 8, 1917 181,456 77
44-P Pavement at Mott Haven, Greenpoint and Gowanus bay Asphalt Construction Co. May 13, 1919 79,720 38
45 Constructing a terminal at Hallets Cove Mohawk Dredge & Dock Co., Inc. Nov. 28, 1919 281,591 41
46 Dockwall at Weedsport Scott Bros. Aug. 31, 1915 11,702 37
47 Dockwall and pavement, Tonawanda and North Tonawanda I. M. Ludington's Sons, Inc. Oct. 5, 1915 36,901 92
49 Grading terminal at Spencerport F. J. Mumm Contracting Co., Inc. Oct. 8, 1915 1,354 30
50 Grading terminal at Holley Rhodey & Clawson Nov. 12, 1915 807 75
51 Dockwall and roadway approaches at Medina Fred H. Rhodey Feb. 16, 1916 4,862 83
52-P Paving on Pier 6, East river, New York city Sicilian Asphalt Paving Co. June 13, 1919 11,252 00
54 Grading terminal site, Middleport Hammond-Tracey Construction Co., Inc. Mar. 27, 1917 1,052 25
55 Pier at Gowanus bay Riverside Contracting Co. Sept. 4, 1917 500,410 28
56 Repairing Pier 5, East river, New York city I. J. Stander & Co., Inc. June 28, 1918 29,794 39
57 Viaduct and approach to Rochester terminal Chas. Kiehm Feb. 25, 1919 93,883 71
58 Building tracks and pavement at Troy, lower terminal C. P. Boland & Co. Dec. 2, 1918 19,481 57
59 Approach tracks to pier, lake terminal, Oswego W. F. Martens May 6, 1918 5,391 41
60 Railroad and crane tracks on pier, lake terminal, Oswego W. F. Martens May 6, 1918 9,119 00
61 Approach tracks to Pier 1, Erie basin, Buffalo Walsh Construction Co. May 15, 1918 10,787 60
62 Railroad and crane tracks on Pier 1, Erie basin, Buffalo Walsh Construction Co. May 15, 1918 10,641 45
63 Pavement at Utica terminal Harry W. Roberts & Co. April 19, 1918 9,490 23
64 Railroad and crane tracks at Schenectady Robert Wetherill Receiver for American Pipe & Construction Co. April 24, 1918 11,022.44
66 Shore protection between Pier 2 and Lake street, Erie basin, Buffalo Empire Engineering Co., Inc. June 29, 1918 12,409 13
67 Approach tracks to Pier 2, Erie basin, Buffalo Walsh Construction Co. July 3, 1918 6,959 60
68 Railroad tracks on Pier 2, Erie basin, Buffalo Walsh Construction Co. July 3, 1918 6,270 30
69 Shore protection between Lake street and Slip No. 1, Erie basin, Buffalo Richard C. Bush Feb. 27, 1919 8,475 53
70 Razing buildings, Rochester Geo. W. Chambers April 9, 1919 3,500 00
71 Completion of viaduct approach to Rochester terminal I. M. Ludington's Sons, Inc. Aug. 24, 1920 365,178 38
76 Yard tracks, Erie basin, Buffalo Mohawk Dredge & Dock Co. Sept. 21, 1920 22,055 70
77 Dredging, Piers 5 and 6, Greenpoint, Long Island City New Jersey Shipbuilding & Dredging Co. May 13, 1919 44,196 50
79 Bulkhead wall and foundations for grain elevator, Henry street slip, Gowanus bay Raymond Concrete Pile Co. Oct. 21, 1920 377,699 68
80 Concrete foundation piers of grain elevator, Oswego Brown & Lowe and Law Brothers Nov. 9, 1920 259,578 64
101 Stiff leg derricks at Albany, Whitehall, Little Falls, Rome, Lockport and Tonawanda Mohawk Dredge & Dock Co. Dec. 18, 1916 39,577 95
102 Semiportal cranes, Pier 6, East river Edward F. Terry Mfg. Co. Jan. 21, 1919 41,406 75
103-A Package freight conveyors at Schenectady and Pier 5, New York Brown Portable Conveying Machinery Co. Oct. 3, 1917 10,102 60
104 Electrical equipment, Greenpoint T. Frederick Jackson, Inc. June 10, 1920 22,611 78
105 Electric wiring, scales, etc., at Pier 6 Lord Electric Co. June 28, 1918 19,395 96
106 Tractor cranes at Erie basin, Buffalo, Tonawanda, Lockport (lower), Lyons, Syracuse, Oswego. Utica, Amsterdam, Schenectady, Troy, Pier 6, Long Island City The John F. Byers Machine Co. Feb. 14, 1918 77,210 00
107 Electrical equipment, Erie basin, Buffalo J. Livingston & Co. Mar. 4, 1919 28,685 91
108 Electrical equipment, Long Island City T. Frederick Jackson, Inc. Nov. 21, 1919 4,644 10
109 Capstans and trolley hoists, Pier 6, East river, W. 53d St. and Utica terminal lock General Electric Co. Aug. 2, 1918 18,755 00
110 Traveling wharf cranes, Pier 6, New York city, two Shaw 4-motor Manning, Maxwell & Moore (Purchased by Superintendent of Public Works)   23,885 00
112 Trailers and hand trucks, Pier 6, Greenpoint, Mott Haven Lansing Company July 23, 1919 9,250 00
113 Capstans and trolley hoists, Greenpoint, Schenectady and Erie basin, Buffalo General Electric Company June 9, 1919 14,090 00
114 Cranes, Erie basin, Buffalo Heyl & Patterson, Inc. Oct. 27, 1920 39,714 00
114-a Furnishing and installing extension to boom of one of cranes at Erie basin, Buffalo Heyl & Patterson, Inc. May 29, 1922 1,300 00
117 Motor generators and switchboards, Mott Haven and Greenpoint Leonard Morey June 20, 1919 5,292 52
124 5-ton full portal revolving jib crane at Troy Walter H. Wilms May 10, 1922 9,998 00
125 5-ton full portal revolving jib crane at Oswego Walter H. Wilms May 10, 1922 9,998 00
126 Clam-shell buckets, New York city Contractors Trading Co., Inc. May 23, 1922 2,770 00
127 Lifting magnet equipment, Troy and Mott Haven K.I. Clisby June 1, 1922 4,190 00
203 Frame freight-houses at Troy, Mechanicville, Fort Edward and Port Henry Collins Brothers Dec. 29, 1916 8,485 68
203-P Plumbing in freight-house, Troy M.J. Flannery & Son Dec. 26, 1919 673 00
204 Frame freight-houses at Schenectady, Amsterdam, Fonda, Ilion and Frankfort Kennedy & Scullen Mar. 12, 1917 19,485 82
205 Frame freight-houses at Utica and Rome Wm. R. Kimmey Mar. 14, 1917 13,665 43
206 Frame freight-houses at Spencerport and Holley J.B. McCabe & Son Jan. 29, 1917 1,397 50
207 Freight-house on Pier 6 I.J. Stander & Co., Inc. Jan 11, 1918 128,500 22
207-H Heating system, freight-house on Pier 6 Miller & Brady, Inc. Mar. 22, 1918 2,664 26
207-P Plumbing and water-supply systems, freight-house, Pier 6 Jarcho Bros., Inc. April 16, 1918 7,334 85
208 Frame freight-houses at Fort Plain and Little Falls Kennedy & Scullen Construction Co. May 7, 1917 9,398 36
209 Frame freight-houses at Tonawanda and North Tonawanda G.J. & P.L. Metzger June 4, 1917 7,542 64
210 Frame freight-houses at Lockport (upper and lower sites) Savage Construction Company June 1, 1917 9,844 48
211 Frame freight-houses at Newark, Albion and Median W.F. Martens & Co., Inc. June 14, 1917 8,044 28
212 Permanent freight-house on Pier 1, Erie basin, Buffalo Felton Construction Company Nov. 14, 1918 196,847 74
212-H Heating system, freight-house, Erie basin, Buffalo Power Efficiency Corporation Dec. 6, 1919 3,540 00
212-P Plumbing, freight-house Pier 1, Erie basin, Buffalo James J. Bresnahan Dec. 6, 1919 3,322 00
213 Frame freight-house and timber derricks at Syracuse Savage Construction Co. Feb. 14, 1918 26,718,22
214 Frame freight-house and paving at Amsterdam Kennedy & Scullen Construction Co. April 26, 1918 15,044 02
216 Frame freight-house on Pier 2, Erie basin, Buffalo Savage Construction Co. July 9, 1918 12,065 00
217 Freight-house and crane-track, Long Island City, N. Jane St. A. E. Norton, Inc. Oct. 23, 1918 84,335 27
217-P Plumbing system, freight-house, Long Island City, N. Jane St. Altman Plumbing Co. May 29, 1919 4,315 62
218 Freight-house at West 53d street, New York city Donnell-Zane Co., Inc. May 13, 1919 45,592 66
219 Freight-house at Gowanus bay Snare & Triest Co. April 30, 1920 606,879 81
219-H Heating system, freight-house, Gowanus bay George Gibson & Co., Inc. June 1, 1921 4,509 80
219-P Plumbing system, freight-house, Gowanus bay Wm. Young Plumbing Co. June 1, 1921 5,918 00
219-W Water-supply system, freight-house, Gowanus bay Thomas E. O'Brien, Inc. Nov. 26, 1921 7,061 00
220 Frame freight-house extension at Utica James T. Young Aug. 12, 1918 5,342 40
221 Frame freight-house extension at Little Falls and frame freight-house at Herkimer Kennedy & Scullen Construction Co. Aug. 30, 1918 6,293 21
222 Frame freight-house and depressed roadway at Canajoharie J. A. LaPorte Aug. 23, 1918 4,206 40
223 Freight-house at Greenpoint Post & McCord Mar. 20, 1919 78,467 32
223-P Plumbing system, freight-house, Greenpoint Thomas E. O'Brien, Inc. Sept. 10, 1920 10,395 00
224 Freight-house at Mott Haven Post & McCord, Inc. July 29, 1920 147,442 31
225 Head-house, West 53d St. pier, New York city Fox, Reynolds Co., Inc. Dec. 5, 1919 58,128 62
225-H Heating, West 53d street head-house Austin Engineering Co. Nov. 12, 1920 5,119 00
226 Frame freight-house, Oswego, river terminal J. A. LaPorte April 28, 1919 5,030 58
227 Frame freight-house, Gowanus bay J. A. LaPorte April 28, 1919 9,305 20
228 Frame freight-house, Rochester W. F. Martens Dec. 27, 1919 13,700 50
228-H Extension to frame freight-house, Rochester Henry B. Reed April 5, 1921 9,531 85
229 Foundation for permanent freight-house, Rochester New England Foundation Co., Inc. Nov. 11, 1920 30,651 46
232 Freight-house at Brockport F. W. & J. J. Crouch Jan. 14, 1922 2,065 50
        ---------------
          Total ......................... ......................... ............... $8,137,186 14

Notes:
    *   Work completed by Superintendent of Public Works.
    † Date of compiling table.
    ‡   Paid to State.



CONSTRUCTION OF BARGE CANAL TERMINALS -- (Continued)
WORK COMPLETED UNDER CHAPTER 585, LAWS OF 1918,*
Chapter 746, Laws of 1911, and amendatory laws
[*This was the act which recompensed contractors for losses sustained by reason of doing work under war conditions entered into before war was declared.]

Con-
tract
No.
Description of work Contractor Date of
contract
Total con-
struction
cost, includ-
ing altera-
tions and
extra work
orders
19 Bulkhead and pier at Greenpoint McHarg-Barton Company Nov. 24, 1916 $289,663 05
20 Channel, harbor, piers, bulkheads and highway bridge at Syracuse Walsh Construction Company Nov. 4, 1915 645,883 55
21 Piers and harbor, Erie basin, Buffalo Empire Engineering Co., Inc. Jan. 12, 1914 928,398 37
26 Pier at Rouses Point John E. Byron & Co. Oct. 30, 1916 23,456 67
31 Dockwall and frame freight-house at Lyons Lupfer & Remick Sept. 30, 1916 56,544 98
36 Dockwall at Cohoes Troy Public Works Company Mar. 27, 1917 30,611 23
48 Dockwall at Rochester Michael H. Ripton Oct. 19, 1916 94,766 44
52 Repairing and extending Pier 6, East river, New York city Kaufman and Garcey July 27, 1916 135,004 70
53 Dockwall and bascule bridge at Ohio basin, Buffalo Walsh Construction Company Oct. 27, 1916 496,420 19
201 Permanent freight-houses at Albany and Whitehall J.A. LaPorte Jan. 2, 1917 84,270 66
        ---------------
          Total ........................... .................... ............ $3,154,857 18


WORK UNDER CONTRACT BUT NOT COMPLETED OCTOBER 18, 1922
Chapter 746, Laws of 1911, and supplementary laws

Con-
tract
No.
Character of work Contractor Date of
contract
Contract price
as modified
by
alterations
53-A Completing certain portions of dockwall, Ohio basin, Buffalo Great Lakes Dredge & Dock Co. Dec. 27, 1920 $435,000 00
81 Grain elevator at Gowanus bay Fegles Construction Co., Ltd. May 3, 1921 1,567,420 04
84 Clarissa street approach, Rochester I. M. Ludington's Sons, Inc. Sept. 7, 1921 63,309 00
86 Fences at Gowanus bay, Greenpoint and West 53d St., New York city Leon Gottlieb Iron Works Mar 18, 1922 8,782 50
87 Fence at Little Falls terminal American Fence Construction Co., Inc. Mar. 14, 1922 4,093 25
88 Paving, railroad and crane tracks, etc., Rochester Terminal I. M. Ludington's Sons, Inc. June 22, 1922 123,240 00
89 Paving, railroad and crane tracks, electrical work, etc., Syracuse terminal J. H. Gallup July 28, 1922 59,609 00
90 Dredging Henry street slip, Gowanus bay Taylor Dredging Co. Aug 1, 1922 19,085 00
115 Power equipment, Gowanus bay The Croker National Fire Prevention Engineering Company, Inc. Jan. 7, 1922 57,359 99
116
(Revised)
Semiportal cranes, W. 53d St. and Greenpoint, New York city Shepard Electric Crane & Hoist Co. Jan. 16, 1920 56,280 00
118 Semiportal cranes, Gowanus bay Lambert Hoisting Engine Co. Oct. 11, 1921 25,590 00
119
(Revised)
[original text has 199]
Burtoning cranes, Mott Haven Lambert Hoisting Engine Co. Oct. 11, 1921 11,980 00
120 Cranes at Rochester The McMyler Interstate Co. Jan. 21, 1922 16,230 00
122 5-ton traveling bridge cranes, one each at Rochester and Syracuse Penn Bridge Co. May 9, 1922 58,300 00
128 5-ton full portal revolving jib crane, Erie basin, Buffalo Walter H. Wilms July 22, 1922 9,998 00
129 Lifting magnets, Schenectady; also Gowanus bay, Mott Haven, Greenpoint and Pier 6, New York city K. I. Clisby Aug. 29, 1922 9,590 00
130 Lifting magnets, Pier 2, Erie basin, Buffalo Electric Controller & Mfg. Co. Aug. 26, 1922 4,512 10
131 Four 20-ton auto truck scales, Gowanus bay, Greenpoint, Mott Haven, Long Island City The Fairbanks Co. Sept. 12, 1922 8,364 25
132
(Revised)
One 5-ton full portal revolving jib crane at Mott Haven Walter H. Wilms Sept. 25, 1922 9,998 00
133 One 5-ton full portal revolving jib crane, Ohio basin, Buffalo Walter H. Wilms Sept. 11, 1922 9,998 00
134 One 5-ton full portal revolving jib crane, Syracuse Walter H. Wilms Sept. 11, 1922 9,998 00
135 Generator sets, one each at Albany and Troy K. I. Clisby Aug. 29, 1922 3,000 00
136 Steel tanks, 23 at Waterford K. I. Clisby Aug. 29, 1922 3,525 00
138 Locomotive crane, Long Island City W. H. Wilms Sept. 20, 1922 8,000 00
230 Permanent freight-house at Rochester W. F. Martens July 7, 1921 182,399 25
230-H Heating, Rochester freight-house L. C. Gresens Dec. 20, 1921 7,295 00
230-P Plumbing, Rochester freight-house Arensmeyer, Warnock & Aahrndt, Inc. Dec. 17, 1921 4,177 00
233 Extension of pier shed West 53d street, New York city McHarg-Barton Co. June 8, 1922 51,355 00
        ---------------
          Total .............................. .............................. ............... $2,828,488 38


SUMMARY OF COST -- CONSTRUCTION OF BARGE CANAL TERMINALS

ITEMS Totals
Work completed up to October 18, 1922, exclusive of that done under chapter 585, Laws of 1918 $8,137,186 14
Work completed under chapter 585, Laws of 1918 3,154,857 18
Work under contract but uncompleted October 18, 1922 2,828,488 38
  --------------------
        Total .................................................. $14,120,531 70


PREVIOUS CHAPTER   |   CONTENTS   |   NEXT CHAPTER
Erie Canal home page   |   Historical Documents page

http://www.eriecanal.org/Texts/Whitford/1921/chap32.html